MULTI-GARD

INSTALLATION PROCEDURES

www.carlonsales.com

The

Multi-Gard belled end

may also be used as a terminator at entrances without

pre-cast terminators.

1. Insert the belled end flush with the inside wall of the vault with print line

facing upward.

2. Insert water tight plugs into unused cells.

3. Insert flared bell fitting to full depth.

4. Seal entrance as required by job specifications.

Use split plugs for sealing Multi-Gard cells where cable has been installed.

The

pass-through terminator

is designed to allow for continuous ducts through

the vault or hand hole for cable pulling.

1. Install terminator into vault following steps 1 through 5 for standard Type 1

terminator.

2. Cut innerduct of pass through kit 10" longer than the width of the manhole.

Add spacers as needed.

3. Upon completion, remove the watertight plugs and install innerducts to

traverse manhole/handhole by cutting to length inserting into one side of

handhole and raising or bowing center of innerduct span to insert into the

pass-through terminator on the opposite side.

Use the

jet terminator

for jetting operations.

1. Remove watertight plugs in order to assure to total insertion.

2. Apply standard grade solvent cement (VC9962) to male end of Multi-Gard.

Install jet terminator to insertion line.