2.3 Enclosure Installation, Ground-mount

Never transport the unit with installed batteries. Doing so can cause injury to the installer or damage

the enclosure and equipment. Install the batteries after you transport the unit to the site and secure

it to the pad.

CAUTION!

ATTENTION:

It is the responsibility of the installer to meet the requirements of all applicable national and local codes. Alpha

Technologies assumes no responsibility or liability for failure of the installer to comply with the requirements of

all applicable local and national codes.

2.3.1 Pre-Installation

Before choosing a location and beginning installation, consider the following:

Provide adequate room for service personnel to remove the doors for battery

installation and removal.
Wherever possible, select a site that is above the 100-year flood plain and away

from residences.
Locate in the shade to minimize the effects of solar loading.

Locate in an area with good airflow.

Locate at least 4" from the backside of the LPE to any wall.

Locate away from sprinkler systems or other sources of forced water.

Locate out of the prevailing wind to minimize the buildup of snow or accumulation

of wind-borne dust.
Avoid locating the enclosure where it will be an obstruction or will inhibit visibility.

Evaluate the soil conditions for suitability for the installation of the grounding

system applicable to your particular installation.
Is utility power cabling run to and terminated at the site?

NOTE:

The appropriate grounding method for a particular location depends on soil type, available space, local codes,