beautypg.com

4 initial commissioning, Initial commissioning – Xylem TURB 430 PORTABLE TURBIDITY METER User Manual

Page 17

background image

Turb 430 IR/T

Commissioning

17

ba75507e03

07/2006

3.4

Initial commissioning

Perform the following activities:

! For

– accumulator operation: insert the accumulator pack (see

section 5.1.2)

– line power operation and charging the accumulator pack: connect

the power pack (see section 3.2)

– operation with LabStation: connect the LabStation and place the

Turb 430 IR/T in the LabStation (see section 3.3)

! Switch on the meter (see section 4.1)
! Set the language as necessary (see section 4.3.3)
! Set the date and time as necessary (see section 4.3.4)

Note
When you set the language, date and time according to the mentioned
sections of this operating manual you will quickly become familiar with
the simple operation of the Turb 430 IR/T.