Figure #26, Leveling band post installation – Grain Systems PNEG-365 User Manual
Page 24

Grain Systems, Inc. Assumption, Ill.
24
18' Manual Batch
REV. 9-30-96
Figure #26
Leveling Band Post
2nd hole from sidewall
Leveling Band Post
6th hole from sidewall
S-277
5/16" x 1.1/4"
Bin Bolt
Optional Rotary Switch
LEVELING BAND POST INSTALLATION
Install the leveling band posts on the floor as shown.
The second and sixth holes in the beam indicate the location of the leveling band posts. Attach posts with 5/16" x
1.1/4" bin bolts (S-277). In the second hole from the bottom of the sheet, there will be 6 posts (1 every third sheet).
In the sixth hole there will be 6 posts (1 every third sheet). After all of the posts have been installed fill the unused
holes with 5/16" x 1.1/4" bin bolts.
See also other documents in the category Grain Systems Conditioners:
- PNEG-1890 (16 pages)
- PNEG-595 (26 pages)
- PNEG-1472 (30 pages)
- PNEG-897 (58 pages)
- PNEG-838 (4 pages)
- PNEG-1755 (36 pages)
- PNEG-524 (24 pages)
- PNEG-1080 (2 pages)
- PNEG-728 (47 pages)
- PNEG-673 (57 pages)
- PNEG-1717 (88 pages)
- PNEG-823 (42 pages)
- PNEG-630-6S (23 pages)
- PNEG-1876 (80 pages)
- PNEG-102 (2 pages)
- PNEG-366 (51 pages)
- PNEG-1626 (1 page)
- PNEG-1874 (78 pages)
- PNEG-1798 (34 pages)
- PNEG-1927 (4 pages)
- PNEG-924 (2 pages)
- PNEG-582 (26 pages)
- PNEG-012 (46 pages)
- PNEG-1797 (86 pages)
- PNEG-546 (26 pages)
- PNEG-951 (102 pages)
- PNEG-1650 (92 pages)
- PNEG-1649 (50 pages)
- PNEG-1376 (88 pages)
- PNEG-361 (46 pages)
- PNEG-338 (32 pages)
- PNEG-1276 (78 pages)
- PNEG-1283 (22 pages)
- PNEG-1089 (14 pages)
- QSG-001 (2 pages)
- PNEG-950 (96 pages)
- PNEG-1590 (3 pages)
- PNEG-501 (33 pages)
- PNEG-1447 (68 pages)
- PNEG-707GSI (446 pages)
- PNEG-349 (32 pages)
- PNEG-236 (22 pages)
- PNEG-743 (16 pages)
- PNEG-900 (54 pages)
- PNEG-1935 (92 pages)