Chapter 7: roof assembly – Grain Systems Tanks PNEG-4060 User Manual
Page 119
24.Attach the appropriate lifting chains (R) to the appropriate lilting device (S).
25.Use the appropriate lifting device (S) and qualified personnel to hoist the cap plate assembly (W)
into place.
26.Ensure all holes are aligned, and install flange bolts (U) and flange nuts (T) into each collar channel
clip.
27.Disconnect the lifting device (S) and remove lifting chains (R) from the cap plate assembly (W).
28.Tighten all hardware to the recommended torque specifications. See
Figure 7-34 Lifting the center collar channel and cap plates
R
Appropriate lifting chains
U
7/16 x 1-1/4 in. flange bolt (S-10250)
S
Appropriate lifting device
V
Tube caulk
T
7/16 in. nut (S-10251)
W
Cap plate assembly, approximately 457 lb (207.29
kg)
29.Secure the cap plate assembly to the center collar using bolts with sealing washers (X) and nuts (Y),
leaving the peak conveyer support bracket holes (Z) unfilled.
30.Replace the four vendor eyebolts with the supplied bolts with sealing washers (X) and nuts (Y).
31.Tighten all hardware to the recommended torque specifications. See
Pneg-4060 60 Ft Diameter 40-Series Bin
119