beautypg.com

Chapter 7: roof assembly – Grain Systems Tanks PNEG-4060 User Manual

Page 109

background image

Chapter 7: Roof Assembly

Before You Begin

Ensure all A-frame roof rafter assemblies are installed, and ensure all intermediate purlins are installed
and properly tightened. Predetermine the manway access location.

What You Should Know

For adjustment purposes, roof panels will be installed to each rafter first, causing exposed gaps between
each roof panel group (see figure below). After all roof panels are installed, ensure that all installed hard-
ware (flange bolts with sealing washers and flange nuts) are tightened to secure the roof panels.

Figure 7-26 Roof panel overview

A

Roof panel (CTR-0184)

B

Exposed gap

1. With assistance, position a roof panel (A) onto the A-frame roof rafter (C), and install a flange bolt (D)

and flange nut (E) securing the upper portion of the roof panel (A).

2. Install five flange bolts with sealing washers (D) and flange nuts (E), into the lower portion of the roof

panel (A), securing the panel to the eave angle.

3. Working in a clockwise direction, continue installing roof panels (A) to each A-frame roof rafter (C),

leaving an exposed gap (B) between each installed roof panel.

Pneg-4060 60 Ft Diameter 40-Series Bin

109