Dryer installation, Chapter 4 dryer installation, Dryer layout foundation – Grain Systems PNEG-1797 User Manual
Page 26: Dryer layout, Foundation

26
PNEG-1797CE CE Approved T-Series Tower Dryer
4. Dryer Installation
Dryer Layout
System Layout
When considering dryer location make allowance for:
1. Grain handling systems.
2. Location of storage bins.
3. Wet grain supply.
4. Prevailing wind direction.
5. Fuel and power supply.
6. Noise.
7. Control panel location.
Site Location
Do not locate the dryer:
1. Inside a building.
2. Adjacent to combustible material which may be sucked in.
3. Within 2.0 m of other structures. Refer to specifications
and dimensions
.
You may need to obtain local permission for the dryer construction and should also consider:
1. Electrical code.
2. Fuel installation regulations.
3. Insurance requirements.
Foundation
Standard foundation details are given in
. For ground
conditions outside of these standards a local engineer will be required to carry out site specific
foundation design.