GAS CONNECTION

The gas supply line can be routed through the knockouts

located on the front of the unit or through the opening provided

in the unit's base. Refer to Figure 9 to locate these access

openings. Typical supply piping arrangements are shown in

Figures 4 and 5. All shaded items are field-supplied.
Two grommets are shipped in the blower compartment (in parts

bag taped to the blower housing) of every unit with gas heat

and should be used in the knockouts when the gas piping

penetrates the front of the unit.
After the gas supply piping has been installed, the bottom

opening should be sealed to prevent water from leaking into the

building.
Gas piping recommendations:

1. A drip leg and a ground joint union must be installed in the

gas piping.

2. When required by local codes, a manual shut-off valve may

have to be installed outside of the unit.

3. Use wrought iron or steel pipe for all gas lines. Pipe

compound should be applied sparingly to male threads

only.

WARNING:Natural gas may contain some propane. Propane,

being an excellent solvent, will quickly dissolve

white lead or most standard commercial com-

pounds. Therefore, a special pipe compound must

be applied when wrought iron or steel pipe is used.

Shellac base compounds such as Gaskolac or

Stalastic, and compounds such as Rectorseal #5,

Cyde's or John Crane may be used.

4. All piping should be cleaned of dirt and scale by hammering

on the outside of the pipe and blowing out the loose dirt and

scale. Before initial start-up, be sure that all of the gas lines

external to the unit have been purged of air.

5. The gas supply should be a separate line and installed in

accordance with all safety codes as prescribed under

“Limitations”. After the gas connections have been

completed, open the main shut-off valve admitting normal

gas pressure to the mains. Check all joints for leaks with

soap solution or other material suitable for the purpose.

NEVER USE A FLAME.

6. The furnace and its individual manual shut-off valve must

be disconnected from the gas supply piping system during

any pressure testing of that system at test pressures in

excess of 1/2 psig (3.48kPa).

The furnace must be isolated from the gas supply piping

system by closing its individual manual shut-off valve

during any pressure testing of the gas supply piping system

at test pressures equal to or less than 1/2 psig (3.48kPa).

7. A 1/8 inch NPT plugged tapping, accessible for test gage

connection, must be installed immediately upstream of the

gas supply connection to the furnace.

L.P./PROPANE UNITS, TANKS AND PIPING

All gas heat units are shipped from the factory equipped for

natural gas use only. The unit may be converted in the field for

use with L.P./propane gas with accessory kit model number

1NP0434.
All L.P./propane gas equipment must conform to the safety

standards of the National Fire Protection Association.
For satisfactory operation, L.P./propane gas pressure must be

10.5 inch W.C at the unit under full load. Maintaining proper gas

pressure depends on three main factors:

1. The vaporization rate which depends on (a) the

temperature of the liquid and (b) the “wetted surface” area

of the container or containers.

2. The proper pressure regulation. (Two-stage regulation is

recommended from the standpoint of both cost and

efficiency.)

3. The pressure drop in the lines between regulators and

between the second stage regualtor and the appliance.

Pipe size required will depend on the length of the pipe run

and the total load of all appliances.

Complete information regarding tank sizing for vaporization,

recommended regulator settings, and pipe sizing is available

from most regulator manufacturers and L.P./propane gas

suppliers.
L.P./propane gas is an excellent solvent and special pipe

compound must be used when assembling piping for this gas

as it will quickly dissolve white lead or most standard

commercial compounds. Shellac base compunds such as

Rectorseal #5 are satisfactory for this type of gas.
Check all connections for leaks when piping is completed,

using a soap solution. NEVER USE A FLAME.

LOW NOx APPLICATION

For natural gas heat installations in locations which require low

Nitros Oxide emmissions, accessory model 1LN0404 must be

installed.

035-14832-003-A-0204

6

Unitary Products Group

FIG. 4 - EXTERNAL SUPPLY CONNECTION

EXTERNAL SHUT-OFF

FIG. 5 - BOTTOM SUPPLY CONNECTION

EXTERNAL SHUT-OFF