Stacking Recommendations
The purpose of this section is to collect notes on recommended procedures and expected behavior
of stacked managed switches. Procedures addressed initially are listed below.
•
Initial installation and power-up of a stack.
•
Removing a unit from the stack
•
Adding a unit to an operating stack
•
Replacing a stack member with a new unit
•
Renumbering stack members
•
Moving the master to a different unit in the stack
•
Removing a master unit from an operating stack
•
Merging two operational stacks
•
Preconfiguration
•
Upgrading firmware
•
Migration of configuration with a firmware upgrade
General Practices
•
When issuing a command (such as move management, or renumber), it is recommended that
the command has fully completed before issuing the next command. For example, if a reset is
issued to a stack member, use the show port command to verify that the unit has re-merged
with the stack, and all ports are joined before issuing the next command.
•
When physically removing or relocating a unit, always power down the unit before
disconnecting stack cables.
•
When reconnecting stack cables, connect them before powering up the unit, if possible, and
insure a good connection by tightening all connector screws (where applicable).