19

HEATEr wiriNG

IF ANY OF THE ORIGINAL WIRE AS SUPPLIED WITH THE

APPLIANCE MUST BE REPLACED, IT MUST BE REPLACED

WITH 105°C WIRE OR ITS EQUIVALENT, EXCEPT IN THE

BURNER HOUSING USE 200°C WIRE.

The power burner is wired to the heater as shown in Figure 11

for GPG models and Figure 12 for GPV models. The model

and rating plate provided the electrical information needed

to size the complete heater branch supply.

All electrical work must be installed in accordance with the

National Electrical Code and local requirements.

When installed, the appliance must be electrically grounded in

accordance with local codes or, in the absence of local codes,

with the National Electrical Code, ANSI/NFPA 70-1987.

DO NOT ENErGiZE THE BrANCH CirCUiT BEFOrE THE

HEATEr TANk iS FiLLED wiTH wATEr.

STArT UP

iMPOrTANT

Factory Start-Up is required for activating warranty and assuring

maximum operating performance. Contact your local sales

representative or Autho-rized Start-Up Agent to arrange a FREE

Certified Start-Up.

If you have not already done so, contact your local State Sales

Representative or Authorized GPG/GPV Start-Up Agent and

set-up a date for the start-up service.

The time to ask any questions you may have about your unit is when

the State Authorized GPG/GPV Start-Up Agent is there. Please do

not hesitate to ask the agent any questions which you may have

regarding the units start-up, operation or maintenance.

CAUTiON

BEFOrE PrOCEEDiNG wiTH THE OPErATiON OF THE

UNiT, MAkE SUrE HEATEr AND SySTEM ArE FiLLED

wiTH wATEr AND ALL Air iS EXPELLED FrOM HEATEr

AND PiPiNG.

NEVER OPERATE THE HEATER WITHOUT FIRST BEING

CERTAIN IT IS FILLED WITH WATER AND A TEMPERATURE

AND PRESSURE RELIEF VALVE IS INSTALLED IN THE RELIEF

VALVE OPENING OF THE HEATER.

FiLLiNG

1. Close the heater drain valve by turning handle clockwise.

2. Open a nearby hot water faucet to permit the air in the system

to escape.

3. Fully open the cold water inlet pipe valve allowing the heater

and piping to be filled.

4. Close the hot water faucet as water starts to flow.

5. The heater is ready to be operated.

PUrGiNG

Gas line purging is required with new piping or systems in which

air has entered.

CAUTiON

PUrGiNG SHOULD BE PErFOrMED By PErSONS

EXPEriENCED iN THiS TyPE GAS SErViCE. TO AVOiD riSk Or

FirE Or EXPLOSiON, PUrGE DiSCHArGE MUST NOT ENTEr

CONFiNED ArEA Or SPACES wHErE iGNiTiON CAN OCCUr.

THE ArEA MUST BE wELL VENTiLATED AND ALL SOUrCES

OF iGNiTiON MUST BE iNACTiVATED Or rEMOVED.

The following test equipment should be on hand: (all test

equipment must be acclimated to ambient temperature before

calibration and use.)

– CO

2

indicator (Fyrite or similar) or O

2

analyzer

– CO indicator (Monoxor or similar)

– Stack thermometer

– Draft Gauge or inlined manometer

– Two U-Tube manometers or calibrated 0-10” and 0-35” w.c.

pressure gauges

– Combination volt/ammeter

• Attach a gas pressure gauge or manometer to upstream side

of main gas cock and a gas pressure gauge or manometer to

the manifold pressure tapping.

• Check voltage at disconnect switch to make certain that it

matches that shown on the burner label.

• Apply a few drops of No. 20 SAE non-detergent oil to motor

bearings.

• Drill max. 5/16” hole in breeching as close as possible to

flue connection on heater to install stack thermometer and

combustion analyzing equipment, see Figure 4.

• You are now ready to begin the burner start-up procedure.