Installation instructions, Installation / commissioning, Lighting the fire – Stovax PR0741 User Manual
Page 23: Commissioning
23
INSTALLATION INSTRUCTIONS
INSTALLATION / COMMISSIONING
10. LIGhTING ThE FIRE
10.1 Locate the control valve on the fire. There are two
control knobs on the valve, the right-hand knob controls the
pilot ignition and the left hand knob controls the main
burner.
10.2 If your fire has already been upgraded to battery remote
control, please refer to the instructions provided with the
upgrade to operate the remote control. The
following instructions will work for either situation.
1
AR0914
10.3 Ensure that the left-hand control knob is pointing to off ( ).
10.4 Ensure that the right-hand control knob is pointing to off ( ).
10.5 Press in the right-hand control knob and rotate it anti-
clockwise until a click is heard (keep pressing in) and the
knob is pointing to pilot (
). The pilot should now
light.
If the pilot has not lit, repeat the procedure until it does.
10.6 Keep the control knob pressed for 10 seconds and then
release it, the pilot should stay alight. If the pilot goes out,
repeat the procedures until it does.
10.7 If the pilot will not light after repeated attempts, contact the
retailer or installer from whom the fire was purchased.
10.8 Turn the right-hand control to point to main burner (
).
The fire can now be controlled using the left hand
control knob.
10.9 Turn the left hand control knob to point to low fire (
),
the main burner will light on low. The burner can
now be controlled between low and high settings. Turn the
control
knob anti clockwise increase the flame height and clockwise
to decrease the flame height.
ThE yELLOw FLAMES wILL APPEAR whEN ThE FIRE hAS GAINED
SUFFICIEnT HEaT - TyPICaLLy 10 To 20 MInUTES.
I
f
the
pIlot
flame
Is
extInguIshed
,
IntentIonally
or
unIntentIonally
,
do
not
relIght
the
applIance
for
at
least
3
mInutes
.
1. COMMISSIONING
1.1 Close all windows and doors to the room, check all
controls, and allow fire to burn on maximum for 5 minutes.
Test for spillage of flue products using a smoke match. Pass
the lighted smoke match along the top front of the draught
diverter, just inside. See diagram 1.
1
AR1378
1.2 If the fire spills, run for a further 10 minutes and re-check.
1.3 If there are extractor fans in the room or adjacent rooms,
the spillage test must be repeated with the extractors
running on maximum.
IF SPILLAGE PERSISTS, DISCONNECT ThE FIRE AND SEEK
ExPErT adVICE.
For future reference record the installation details on the
commissioning sheet on page 3 of these instructions.