8.1.7 EPO (Emergency Power Off) Input contact
4
1
3
2
3
2
1
SGT5
000_1
00-15
0_Customer inter
fa
ce
EPO
_0
1
4
XB
J2
JP3
Fig. 8.1.7-1 Terminals for connection EPO
An external Emergency switch (Normally
Closed voltage-free contact) can be connected
on terminals XB / 1 - 4 or connector J2 / 12 -
25 of the P4 - Interface Customer.
Remove the cable short-circuiting terminals
XB 2 - 3) when using this external switch.
To enable this function, remove cable short-circuiting XB / 2 - 3 on the
Terminal XB and the Jumper JP3 on P4 – Customer Interface, when the
cables have been already connected on XB or J2.
In a parallel system a separate NC (Normally Closed) contact must be
connected individually to each unit.
When opened, this contact causes the immediate opening of the Contactors K3, K4, K6, K7
and K8, as well as the shutdown of Rectifier, Inverter and Static-Switch.
Be aware: The reliability of the system depends on this contact!
After closure of the Emergency contact, a reset is necessary to enable the restart of
the UPS, by pressing the key “O” (inverter off) on the control panel.
In case of a parallel system press the key “O” (inverter off) on the
control panel of each unit connected on parallel bus and having it’s
output switch Q1 closed.