7 boiler fixing

7.1 Hanging bracket fixing

Reposition the wall template over the flue hole and mark

the position of the fixing holes for the hanging bracket, see

diagram 7.1.

Mark and drill the fixing holes and secure the hanging bracket

which is supplied in the polystyrene base pack.

noTe: Due to the varied site conditions we do not supply

fixings and advise that the installer should supply those which

are suitable.

7.2 boiler Hanging

IMPoRTanT: With regards to the Manual Handling

Operations, 1992 Regulations, the following lift operation

exceeds the recommended weight for a one man lift, refer to

section 15 Manual Handling.

Lifting the boiler into position, lean the top of the boiler slightly

to the wall and position just above the hanging bracket. Lower

the boiler slowly and engage onto the hanging bracket, see

diagram 7.2.

Remove the polystyrene base support.