Installing hardware options

Install any hardware options before initializing the server. For options installation
information, refer to the option documentation. For server-specific information,
refer to "Hardware options installation (on page

57

)."

Installing the server into the rack

20.41 - 27.22 kg

47.18 - 60.0 lb

WARNING: To reduce the risk of personal injury or damage to the
equipment:

Observe local occupation health and safety requirements and
guidelines for manual handling.

Obtain adequate assistance to lift and stabilize the chassis
during installation or removal.

The server is unstable when not fastened to the rails.

When mounting the server in a rack, remove the power
supplies and any other removable module to reduce the overall
weight of the product.

CAUTION: Always plan the rack installation so that the

heaviest item is on the bottom of the rack. Install the heaviest item first,
and continue to populate the rack from the bottom to the top.

1. Install the server into the rack. Refer to the installation instructions that ship

with the 2U Quick Deploy Rail System for more information.

2. Install the cable management arm into the rack.

NOTE: If the cable management arm is mounted on the right side of
the rack, you will have to remove it when adding or replacing a
redundant hot-plug power supply.

3. Connect peripheral devices to the server.