3 reconnecting the inverter, Reconnecting the inverter – SMA SC 500CP XT Installation User Manual
Page 38
![background image](https://www.manualsdir.com/files/818313/content/doc038.png)
5. Open the measurement and disconnect terminals.
6. Ensure that no voltage is present.
7. Cover or isolate any adjacent live components.
6.3
Reconnecting the Inverter
6.3.1
Reconnecting the Supply Voltage and External Voltages
1. Close the measurement and disconnect terminals.
2. Switch on the motor-protective circuit-breakers of the grid
monitoring.
3. Connect any additional external voltage.
4. If the supply voltage has been disconnected downstream from the circuit breaker, switch the external circuit
breaker of the supply voltage on.
Tip: The external circuit breaker of the supply voltage is usually located in a subordinate distribution station.
6 Disconnecting and Reconnecting
SMA Solar Technology AG
Operating Manual
SCCPXT-IA-E4-en-44
38
This manual is related to the following products: