6. Fasten the two screws using an Allen key (AF 3)

(torque: 2 Nm ± 0.2 Nm).

7. Turn the DC load-break switch to the position I.

8. Switch on the circuit breaker of all three line conductors.

☑ All three LEDs start to glow and the start-up phase begins. The start-up phase may take several

minutes.

☑ The green LED is glowing. Feed-in operation begins.

✖ The green LED is flashing?

Possible cause of error: the DC input voltage is still too low or the inverter is monitoring the
utility grid.

• Once the DC input voltage is sufficiently high and the grid-connection conditions are met,

the inverter will start operation.

✖ The red LED is glowing?

• Rectify the error (see the service manual at www.SMA-Solar.com).

7 Commissioning

SMA Solar Technology AG

Operating Manual

35

STP20-25TL-BE-en-12

This manual is related to the following products: