7 commissioning, 1 commissioning procedure, 2 configuring the country data set – SMA 20000TL User Manual
Page 32: Commissioning, Commissioning procedure, Configuring the country data set, 7commissioning
7
Commissioning
7.1
Commissioning Procedure
Before you can commission the inverter, you must check various settings and make changes if
necessary. This section describes the procedure and gives an overview of the steps, which must
always be performed in the prescribed sequence.
Procedure
See
1.
Connection to the SMA Speedwire/Webconnect data
module
Installation manual of the
SMA Speedwire/Webcon-
nect data module
2.
Check which country data set the inverter is set to.
Supplementary sheet with the
default settings, type label or
display
3.
If the country data set is not set correctly for your country
or your purpose, adjust to the required country data set.
4.
Commission the inverter.
7.2
Configuring the Country Data Set
Set the country data set appropriate for your country or purpose within the first ten feed-in hours via
the rotary switches in the inverter. After the first ten feed-in hours, the country data set can only be
changed by means of a communication product.
The country data set must be set correctly.
If you select a country data set which is not valid for your country and purpose, it can cause a
disturbance in the PV system and lead to problems with the grid operator. When selecting the
country data set, you must always observe the locally applicable standards and directives as
well as the properties of the PV system (e.g. PV system size, grid-connection point).
• If you are not sure which country data set is valid for your country or purpose, contact
your grid operator for information on which country data set is to be configured.
7 Commissioning
SMA Solar Technology AG
Operating Manual
STP20-25TL-BE-en-12
32