Installation of tes and mi cable – Thermon TESH User Manual
Page 11
INSTALLATION GUIDELINES SERIES HEATING CABLES
PAGE 9
THERMON...The Heat Tracing Specialists
®
TEP0118U-1111
With a single or two phase system: unroll the
cable, loop it and lay it alongside the pipe
section, so that both passes can be installed
simultaneously.
Note:
First attach the cold lead connection to the pipe
before unrolling the heating cable.
With a 3-phase system: unroll the cable and lay
it alongside the pipe section. The cables can be
installed separately or simultaneously.
Note:
First attach the cold lead connection to the pipe
before unrolling the heating cable.
Temporarily secure the heating cable to the pipe at
approx. 3 m. interval, using SS tie wire / FT fixing
tape, starting with the cold lead section (power
end) and working towards the end of the pipe.
Loops of cable for the recommenend allowance
are to be left at each heat sink - valve, flange,
pump, pipe support etc.- until final fixing of the
cable. For installation on valve, pipe support etc.
see page 12 and further.
1
2
3
heating cable
150 mm
150
cold lead
connection
SS tie wire /
FT fixing tape
cold lead
connection
SS tie wire /
FT fixing tape
heating cable (3x)
+/- 3 m
SS tie wire /
FT fixing tape
Installation of TES and MI cable
150 mm
150