Installation instructions for qualified personnel

Observe the manuals for the

indoor unit and outdoor unit

when installing the entire

system.

Transport the unit in its original

packaging as close as possible

to the installation location. This

avoids transportation damage.

Check the contents of the

packaging for completeness

and check the unit for visible

transport damage.

Immediately notify any

deficiencies to the contractual

partner and forwarding agent.

Lift the unit at the corners

and not by the refrigerant or

condensation connections.

The refrigerant pipes (injection

and suction pipe), valves and

connections to make them

tight against vapour diffusion.

If necessary, also insulate the

condensation line.

Select an installation location

which allows air to freely

flow through the inlet and

outlet (see section "Minimum

clearances")

Do not install the unit in

the immediate vicinity of

devices with intensive thermal

radiation.

Installation near thermal

radiation reduces the unit

output.

Only open the stop valves

for the refrigerant pipes after

installation has been fully

completed.

Seal off open refrigerant pipes

with suitable caps or adhesive

strips to avoid the infiltration

of moisture and never kink or

compress the refrigerant pipes.

Avoid unnecessary bends. This

minimises the pressure loss

in the refrigerant pipes and

ensures that the compressor

oil can flow back without

obstruction.

Make special preparations

regarding the oil return if the

outdoor unit is located above

the indoor unit.

(see section Oil return

measures).

Add refrigerant if the basic

length of the refrigerant pipe

exceeds 5 metres.

For the quantity of additional

refrigerant, refer to chapter

"Add refrigerant".

Only use the union nuts for the

refrigerant pipes included in

the delivery, and remove them

shortly before connecting the

refrigerant pipes.

Establish all electrical

connections connections in

accordance with the relevant

DIN- and VDE standards.

See electrical connection

diagram Ensure the electrical

cables are properly connected

to the terminals, otherwise

there is a risk of fire.

Important information
prior to commissioning

Always pay attention to the
affiliation of the electrical and
refrigerant pipes!
The connections of the
individual circuits may not be
mixed up.
A mistake in this area can have
fatal consequences!

CAUTION

Label the refrigerant pipes
(injection and suction pipes)
as well as the associated
electrical control lines of each
interior unit with a letter.
Only connect the lines to their
associated connections.

NOTE

Wall openings

The wall breakthrough must

have a diameter of min.

diameter of min. 70 mm and

a fall of 10 mm from inside to

outside for each indoor unit.

We recommend that the

inside of the hole is padded or

lined, e.g. using a PVC tube,

to prevent the pipes being

damaged.

(Page 11, figure 1).

After installation has been

completed, use a suitable

sealing compound to close

off the wall breakthrough

(responsibility of customer) .

Do not use materials containing

cement or lime!

Installation material

The outdoor unit is fastened with

4 screws and a wall bracket to the

wall or fixed by a floor bracket to

the ground.

Only use fixing materials
which are suitable for the
given application.

NOTE

Different refrigerant pipes are
required depending on the
cooling output of the indoor
unit.

NOTE

REMKO MVT