You have received i.Net OPs pre-numbered – see label on each i.Net OP indicating its sequence

number. Check and install each respective i.Net OP according to the drawing.

i.Net OPs are hung from the ceiling using the attached chain (supplied by Lencore). Chain length

should be cut to enable each speaker to hang 6-12” above the ceiling tile or 3” below the

ceiling deck. Make sure air can circulate around the i.NetOP and that the i.Net OP is not

touching metal in the ceiling or plenum.

NOTE: Keep the chain lengths/heights consistent throughout the installation and space.

IMPORTANT: Lencore suggests installing equipment in this sequence:

Climb ladder and access the ceiling plenum

Hang i.Net OPs in plenum area at marked locations using preferred hanging

method (powder action gun such as a Hilti-gun™ or drill and screw; check

your local building codes for allowable hanging methods and standards)

Drive nail holding clip to i.Net OP chain and i.Net OP into ceiling

NOTE: Do not permit the i.Net OPs to touch any other metal in the ceiling. Isolate

each i.Net OP with wire ties.