Operating Manual: PMCtendo AC

12-3

Derating

When dimensioning the drive you should take into account the factor K

total

. It is

calculated from the factors K

height

, K

temp

and K

duty

:

K

total

= K

height

* K

temp

* K

duty

The factor K

total

can be used to calculate the permitted torque:

Permitted torque = K

total

* Rated torque M

N

Derating diagram: Installation height

Rated tor

que M

N

[%]

0

20

40

60

80

100

120

500

1000

1500

2000

2500

3000

3500

Installation height [m above sea level]

K

height

Example:

Installation height = 2000 m above sea level

According to the diagram (Fig. 12-1), at this installation height the permitted torque is
approx. 90 % of the rated torque M

N

.

This gives the following for factor K

height

:

K

height

= 0.9.

Fig. 12-1: Permitted torque in relation to installation height