1.
Start drilling unit engine.
2.
Using tethered ground drive controller, pull power mode switch into low position.
3.
Move drilling unit to rear of trailer and align with ramps.
4.
Slowly drive unit onto trailer until track reaches chock.
5.
Lower drill frame to drill frame rest.
6.
Back unit until front of drill frame is seated in rest.
7.
Lower stabilizers to trailer floor.
8.
Stop engine.
9.
Attach tiedowns at rear of unit where indicated on page 86.
Without Tiedown Kit
1.
Start drilling unit engine.
2.
Using tethered ground drive controller, pull power mode switch into low position.
3.
Move drilling unit to rear of trailer and align with ramps.
4.
Slowly drive unit onto trailer until track reaches chock.
5.
Lower stabilizers to trailer floor.
6.
Lower drill frame to trailer floor.
7.
Stop engine when unit is safely positioned on trailer bed for proper tongue weight.
8.
Attach tiedowns to drilling unit where indicated on page 86.
Crushing weight. If load falls or moves it could kill or crush you. Use
proper procedures and equipment or stay away.
NOTICE:
•
Load and unload trailer on level ground.
•
Verify that trailer wheels are blocked.
•
Incorrect loading can cause trailer swaying.
•
Attach trailer to vehicle before loading or unloading.
•
Ten to fifteen percent of total vehicle weight (equipment plus trailer) must be on tongue to help