beautypg.com

NORAC UC4+BC+HD4 Part 1 User Manual

Page 31

background image

27

4.10.1 General Installation Instructions using the 44658-51

Figure 29: Cable Routing Overview (Using 44658-51)

1. Connect the UC4 power cable (C10) to the

UC4+ Control Panel in the cab. Ensure that
both plugs (P16 and P4) are connected to
the panel.

2. Route the 22-pin AMP receptacle (R22) of

C10 to the exterior of the cab.

3.

Connect the 22-pin AMP plug (P22) of

the extension cable (C11) to R22 of C10.
Connect at the hitch. This connection will
provide your hitch disconnect.

4.

Run cable C11 from the hitch to the rear

of the sprayer.

5.

Install the sensor branch cable (C02)

along the boom between the ultrasonic
sensors. Be sure to route the cable through

the boom to avoid damage to the cable
during field operation or boom folding.
Connect cable C02 to cable C02A. Connect
cable C02A to cable C11.

6. Route the 6-pin and 4-pin tower connectors

(T6 and T4) of C11 in the vicinity of the
Job-com box.

Ensure power to the Job-com is

turned off.

7. If the sprayer uses one forward/reverse valve

and a number of cartridge valves (HARDI
DH) turn ON the DIP switch of C12A
(Figure 30). Otherwise leave the switches
OFF (HARDI DAH). There is denotation on
the switch. Turn BOTH switches either ON
or OFF.