Talkaphone ETP-MT/R OP4D Radius Emergency Phone Tower with Dual CCTV Arm User Manual
Etp-mt/r anchor bolt installation instructions
ETP-MT/R Anchor Bolt Installation Instructions
Copyright 2009 Talk-A-Phone Co. All rights reserved.
Talk-A-Phone
Co.
• 7530 North Natchez Avenue • Niles, Illinois 60714-3804
Rev. 7/27/09
Phone 773.539.1100 • Fax 773.539.1241 • [email protected] • www.talkaphone.com
All prices and specifications are subject to change without notice.
Talk-A-Phone, Talk-A-Lert, Scream Alert and WEBS are registered trademarks of Talk-A-Phone Co.
I. Introduction
Note: This manual is for anchor bolt installation only. For instructions on installing the tower onto the anchor
bolts, see the ETP-MT/R Tower Installation Instructions.
II. Contents
Before beginning installation, make sure you have all the included components. Each Tower consists of three
packages. Package #1 is the anchor bolt kit labeled MT/R BOLT KIT. Package #2 is labeled TOWER PTS,
TOWER PTS 24V or OP4 TOWER PTS. Package #3 contains the tower itself.
Anchor Bolt Install Kit
QTY Part
Number
Description
4 42838
J-Bolts
1 26312
Cardboard
Template
Tower Install Kit (keep for use when installing the tower)
QTY Part
Number
Description
8 42839
3/4"-10
Hex
Nut
8 42840
3/4"
Washer
3
42841
10-24 x 3/4" panhead tamperproof screw
2 42843
6-32
hex
nut
1 67478
Polycarbonate
light
cover
1 68590
LED
light
board (12-24V AC/DC - 120VAC)
1
ETP-EL-L or ETP-EL12/24
Long Cord 120VAC Strobe Light or 12/24V AC/DC Strobe Light
III. Installation
1. Electrical and telephone line conduits should be run through the foundation and into the center 4"
diameter hole of the tower.
NOTE: To insure proper grounding of all electrical components, the tower mount should be effectively
earth grounded from the grounding stud (located across from the lower access panel) with 6 AWG or
better insulated, stranded copper wire to the metallic power service raceway (conduit) or an 8 foot or
longer corrosion-resistant ground spike. It is the installer's obligation to ensure compliance with all
national, regional, and local regulations.
2. Pour the foundation at least 2 feet in diameter and 3 feet deep according to your local code and frost
line (see foundation drawing on following page).
3. Install the four (4) 3/4” - 10 x 24 long anchor bolts below grade with five inches (5”) projecting
above grade (see foundation drawing on following page). Use the template provided to properly
position the bolts within the concrete foundation.
NOTE: Make sure all connections meet National, Regional, and Local Electric Codes.