Inspection and Start-up Checklists
Receiving and Inspecting
Unit received undamaged
Unit received complete as ordered including accessories
Handling and Installing
Unit mounted on solid level surface
Sufficient space allowed for access to unit and accessories
Proper electrical service
provided
Hot water provided to humidifier
Drain lines and trap installed properly
Ductwork, fittings and grilles installed properly
All cold duct surfaces insulated
Low ambient control included if freezing condition present
No obstructions to air
flow to condenser
Starting-up the Unit
General visual inspection looks good
All wiring connections checked
All ducts, grilles and panels in place
Start unit
Check ducts and connections for air leaks
Balance air distribution
Confirm condenser airflow is unrestricted
Verify cooling and heating operation
Check for excessive noise or vibration