18
OTR Truck Scale Assembly Instructions
Before the weigh module wiring can be completed, all load cell cables have to be routed through the conduit
beginning at the load cell outlet. Use the following steps to route load cell cables through conduit to the J-box:
1. Before routing load cell cables, mark each load cell cable at the end to help identify each load cell.
2. Carefully make a loop in the flex conduit and position the end of the flex conduit close to the end of the
rigid conduit.
Figure 5-3. Load Cell Pocket Conduit Installed
3. Working from the J-box end, insert a fish tape or similar tool and pull each load cell cable through the rigid
conduit until all excess cable is taken in. When all load cell cable is pulled through, insert end of the flex
conduit over the end of the rigid conduit and tighten fitting.
4. Wire each load cell to the J-box terminal strip in accordance with the wiring code contained in the
Certificate of Conformance.
Load cell cable may be cut for best fit. Standard warranty will not be affected.
Figure 5-4. J-box Pocket
Figure 5-5. Conduit Connection Between Deck Modules
Note