0 calibration, Calibration, Rate speed totalizer load tn/hr ft/min lb/ft tn – Rice Lake BCi Belt Scale - Calibration Guide User Manual
Page 7: Softkey, Softkey from the supervisor’s menu, The integrator will change the softkeys to

Calibration
3
3.0
Calibration
To begin calibration, press the
Supervisor Mode
softkey.
05/30/2013
08:13AM
Supervisor
Mode
Reset
Totalizer
SCALE #1
Diagnostics
Rate
Speed
Totalizer
Load
tn/hr
ft/min
lb/ft
tn
Belt Scale SW PN 154789 1.00
Figure 3-1. Supervisor Mode Softkey
3.1
Speed Sensor Calibration (Belt Sensor Calibration)
Use the following steps to calibrate the speed sensor.
1. Press the
Belt Calibration
softkey from the supervisor’s menu.
Exit=>
SCALE #1
Master
Totalizer
Integrator
Calibrati
5/30/2013
08:13AM
Admin. Passcode (numeric)
Scale Capacity (Max Rate)
Load Cell MV
Total LC Build
Rate Unit Time
Filter (s)
Filter Threshold (divisions)
Speed Unit Time
Fixed Speed
Unit of Measure
420.00
1.99900
800
hr
7.0
2
min
0.00
ft
Belt
Calibration
Time/Date
Figure 3-2. Belt Calibration Softkey
2. The integrator will change the softkeys to
Start, Finish
and
Exit
.
Exit=>
SCALE #1
Start
Finish
5/30/2013
08:15AM
Admin. Passcode (numeric)
Scale Capacity (Max Rate)
Load Cell MV
Total LC Build
Rate Unit Time
Filter (s)
Filter Threshold (divisions)
Speed Unit Time
Fixed Speed
Unit of Measure
420.00
1.99900
800
hr
7.0
2
min
0.00
ft
Figure 3-3. Start, Finish and Exit Softkeys
A reference point needs to be marked on the conveyor belt and a reference point needs to be marked on the
conveyor frame. This will give the operator a reference to count the number of revolutions the belt travels
during the speed calibration. The more revolutions in a test, the better the speed and distance accuracy.