Ridge planting, Liquid fertilizer option, Figure 1-3 – Great Plains PT8030 V1013 Operator Manual User Manual
Page 13: Ered into planting position. see figure 1-3

Figure 1-3
Leveling the Planter
14956
Top of Hopper Support Level with Ground
11
Section 1 Planter Preparation and Setup
PT6030 and PT8030 Pull-Type Planter 401-032M-A
10/10/12
Great Plains Mfg., Inc.
Ridge Planting
To prepare the planter for ridge planting, you must lower
the gauge wheels by inverting the cylinder mounting
blocks.
To invert, refer to Figure 1-4.
1.
Block up the frame to remove weight from tires.
2.
Remove the four 5/8-inch cap screws.
3.
Invert mounting blocks and re-install cap screws.
Torque to specification as listed on the Torque Values
Chart, “Appendix” on page
52.
Figure 1-4
Ridge Planting Adjustment
14958
Liquid Fertilizer Option
The pump should always be mounted even with or lower
than the fertilizer tank.
Hose arrangement is important for efficient pump opera-
tion. If you will be using fewer hoses than there are on the
pump, remove pump hoses from near the center of the in-
take manifold (1) and cap the intake ports (2).
Figure 1-5
Removing Squeeze Pump Hoses
12409
1
2