Installing Power Wiring
4-1
C
HAPTER
4
Installing Power Wiring
This chapter describes how to connect 120 volt DC input power to a 1 HP or 5 HP
GV3000/SE Solar Turbine drive. Guidelines for motor lead lengths are also provided.
Please refer to instruction manual D2-3360 for complete information on wiring a
GV3000/SE drive.
4.1
Installing Fuses for Branch Circuit Protection
Install the required, user-supplied branch circuit protection fuses according to the
applicable local, national, and international codes (e.g., NEC/CEC). The fuses must
be installed in the line before the drive input terminals. See figure 4.1. Fuse value
recommendations are provided in table 4.1.
4.2
Installing a Required External/Separate Input
Disconnect
An input disconnect must be installed in the line before the drive input terminals in
accordance with local, national, and international codes (e.g., NEC/CEC). The
disconnect should be sized according to the in-rush current as well as any additional
loads the disconnect might supply. The trip rating for the inrush current (10-12 times
full load current) should be coordinated with that of the input isolation transformer, if
used. Refer to instruction manual D2-3360 for additional information.
!
ATTENTION: Most codes require that upstream branch protection be
provided to protect input power wiring. Failure to observe this precaution
could result in severe bodily injury or loss of life.
Table 4.1 – Recommended Input Line Fuse Ratings
Drive HP Rating
Input Voltage (+/- 10%)
Fuse Rating
1
1.Recommended fuse type: UL Class J, 600V, time delay, or equivalent.
1 HP
120 VDC
25A
5 HP
120 VDC
70A