Start Using the Controller
Chapter 3
3.
Verify that the image in nonvolatile memory (that is, the project on the
memory card) is the project that you want to load.
4.
Click Load.
After clicking Load, the project is loaded to the controller as indicated by
the controller status indicators.
.
TIP
If no project is stored on the memory card, a message in the lower-left corner
of the Nonvolatile Memory tab indicates that an image (or project) is not
available as shown here.
TIP
For information to change the project that is available to load from nonvolatile
memory, see the Logix5000™ Controllers Nonvolatile Memory Programming
Manual, publicat
.
With these controllers
These indications show the store status
1756-L6x
While the load is in progress, the following occurs:
• OK indicator on the controller is flashing green
• A dialog box in the Logix Designer application indicates that the store is in
progress
When the load is complete, the following occurs:
• OK indicator on the controller is momentarily red, then solid green
1756-L7x
While the load is in progress, the following occurs:
• OK indicator is solid red
• SD indicator is flashing green
• LOAD is shown on the status display
• UPDT can be shown on the status display if the firmware is also updating with
the load
• A dialog box in the Logix Designer application indicates that the store is in
progress
When the load is complete, the following occurs:
• OK indicator on the controller is momentarily red, then solid green
• SD indicator on the controller is Off