Clip-loc – Metal Sales Clip-Loc Installation User Manual
Page 59

CLIP-LOC
© Metal Sales Manufacturing Corporation/ Subject to change without notice/ Effective Date 2/03
812.246.1935 (Corporate Offi ce) • www.mtlsales.us.com
58
R
IDGE
(O
PTIONAL
) O
VER
O
PEN
F
RAMING
1. Once panels have been installed, slide Clip-Loc Turn-up Tool over end of panel and bend pan up until flush with top of panel rib.
Turn up all Clip-Loc pans on both sides of ridge (see page 19).
2. Apply a row of Double Bead Tape Sealant across panel, up and over all ribs approximately 4"-6" from panel end on both sides
of
ridge.
3. Install a Clip-Loc Outside Closure over tape sealant. Before continuing, make sure closure placement will accommodate Clip-
Loc Ridge flashing. Set closure in tape sealant.
4. Once all closures have been installed, place a row of Double Bead Tape Sealant across the top of closures on both sides of ridge.
5. Place Clip-Loc Ridge on top of panel ribs and mark the ridge flashing at the center of each panel rib as a guide for notching. Use
Clip-Loc Notching Tool to notch out ridge flashing (see page 19).
6. Install ridge flashing and secure to Clip-Loc panel rib with a ¼-14 x
7
/
8
" Stitch XL 8" o.c. at every rib.
7. If two or more flashings are required, lap the flashing over the previously installed flashing by a minimum of 2" placing a bead
of tube sealant between the flashings and securing with pop rivets 2
1
/
2
" o.c.
Double Bead Tape Sealant
#
1
/
4
-14 x
7
/
8
" Stitch XL (8" o.c.)
Clip-Loc Panel
Clip-Loc Clip
Clip-Loc Outside Closure
Clip-Loc Ridge
Double Bead Tape Sealant
2" MAX.
C
L
12" MAX.
1:12 Slope
Minimum
INSTALLATION NOTES
Clip-Loc panel must be anchored to solid deck behind outside closure at all ridge, hip, endwall, and peak
conditions to fi x the panel when using this fl oating eave detail.