36
POST FRAME
& RESIDENTIAL
INSTALLATION OVERVIEW
Prevailing
Winds
As shown below with the number designations, install panel against the prevailing wind.
Make sure panels are square and plumb, to assure straight and proper alignment of the entire row of panels.
For areas with high wind considerations, closer fastener spacing may be required.
It is necessary to attach a temporary guide to the foundation to use as an alignment guide when installing siding panels.
Siphon groove side of panel must be overlapped with the non-siphon groove side of the adjacent panel (if applicable).
INSTALLATION OVERVIEW
1
2
4
3
VALLEY DETAIL
(SEE PAGE 40)
RIDGE DETAIL
(SEE PAGE 39)
EAVE / GUTTER DETAIL
(SEE PAGE 37, 38, 40)
CHIMNEY DETAIL
(SEE PAGE 41)
ROOF PENETRATION
(SEE PAGE 41)
HIP DETAIL
(SEE PAGE 39)
GABLE DETAIL
(SEE PAGE 39)