Step 1 step 2, Post frame panel installation – Metal Sales Pro-Panel II Installation User Manual
Page 29
![background image](/manuals/567676/29/background.png)
© Metal Sales Manufacturing Corporation / Subject to change without notice / Effective 5/09.
28
POST FRAME
& RESIDENTIAL
1. Apply a row of Tape Sealant across the top leg of the Eave Molding along the width of the
building.
2. Align and place Inside Closures over the Tape Sealant. It is critical that Inside Closures are
square to building as this will control the alignment of the panels. (See page 24 to check
building square).
3. Apply a row of Tape Sealant across the top of the Inside Closure (Not shown for clarity).
POST FRAME PANEL INSTALLATION
NOTE:
-Eave Molding, Gutter and Valley Flashings must first be installed before panel installation can begin.
-Panels can be installed going from either letf to right or right to left / looking from eave to peak.
INSTALLING FIRST PANEL
INSTALLING INSIDE CLOSURES
1. Install the first panel over the Inside Closure allowing desired overhang. Make sure the panel is
square to the eave and rake.
2. Fasten through panel, closure, and sealants into decking with appropriate amount of fasteners to
meet local building code. (See fastening patterns on pages 13 and 14). Fasteners must penetrate
closure and sealant.
3. After securing panel at eave, repeat the fastening pattern at all panel support locations.
STEP
1
STEP
2
FASTENER
INSIDE CLOSURE
w/ TAPE SEALANT
TAPE SEALANT
INSIDE CLOSURE
ROOF PANEL