THE BOILER IS TOP-HEAVY. Do not

allow it to tip over.

1.

Remove the sleeve.

2.

Remove the contents from the skid, except

the boiler.

3.

Remove the four (4) hex-drive lag screws

holding the boiler to the skid (Figure 1-a).

1. UNPACk THE CRATE

4.

Tip the boiler and shimmy it off the skid.

2. POSITION THE BOILER

WARNINGS

1.

Slide the boiler into desired location.

2.

Meet the minimum clearances to

combustible construction per the
Specification Section of this manual.

OBSERVE MINIMUM CLEARANCES to

combustible walls and ceilings to avoid potential

fire hazard.

DO NOT INSTALL ON CARPET. This may cause

a fire.

INSTALLING THE BOILER NEAR A SOURCE OF

FLAMMABLE LIQUIDS or gases may cause fire or

explosion.

CLEAN BURNERS DAILY if operating the boiler in

a dusty environment.

PROTECT IGNITION SYSTEM COMPONENTS

from sources of water that may spray, drip, or rain

on them during installation or service.

3.

Allow 24" service clearance in front and on

the left side of the boiler.

4.

Level the boiler, using shims as necessary.

1-b