Scheduling Virtual Copy Analysis Tasks

You can schedule Virtual Copy analysis tasks according to a specified schedule.

To add a scheduled Virtual Copy analysis task:
1.

From the Tree view pane, select either a server or node cluster.

2.

Click the Scheduler tab.

3.

Click the Analyze All Virtual Copies tab.

4.

Click Add.

5.

Follow the wizard to complete the scheduling tasks and click Next.

Figure 48 Schedule Virtual Copy Analysis Task Wizard

6.

Set the values for the following applicable options:

Task name

Analyze and clean up all Virtual Copies

Figure 49 Schedule Virtual Copy Analysis Task Details

7.

Set the values for the Schedule, Date, and Time and click Next.

46