GENERAL OPERATING

PROCEDURE

1. Connect fluid supply to applicator.

2. Adjust fluid (FLD), shaping (SHP), and atom-

ization (ATM) pressures as desired using knobs

on the front of the Aerobell Control Module.

3. Turn FLD, SHP, and ATM air toggle switches ON.

4. Turn electrostatic power supply on.

5. Turn trigger (TRG) air toggle switch ON to begin

spraying.

6. When finished, turn TRG, FLD, SHP, and ATM

toggle switches OFF. Turn the electrostatic power

supply OFF.

GENERAL CLEANING

PROCEDURE

1. Turn electrostatic power supply OFF.

2. Connect solvent supply to the applicator.

3. Turn FLD, SHP, and ATM air toggle switches ON.

4. Turn DUMP air toggle switch to ON position.

5. Flush until line is clean.

6. Turn DUMP air toggle switch to OFF position.

7. Turn trigger (TRG) air toggle switch to ON

position.

8. Flush until applicator is clean.

9. Turn TRG, FLD, SHP, and ATM air toggle

switches to OFF position.

APPLICATOR ONLY

CLEANING PROCEDURE

(Aerobell 33 Only)

With the additional solvent valve at the applica-

tor, it is possible to clean the Aerobell 33 without

having to flush the entire line. To do this perform

the following:

1. Turn electrostatic power supply OFF.

2. Turn FLD, SHP, and ATM air toggle switches ON.

3. Turn SOLVENT air toggle switch to ON position.

4. Flush until applicator is clean.

5. Turn DUMP air toggle switch to ON position.

6. Flush until dump line is clean.

7. Turn DUMP, SOLVENT, FLD, SHP and ATM

air toggle switches to OFF position.

9040 Aerobell Control Module - Operation

21

Ransburg

CP-02-01.2