2: The deck channel is then placed into position. A 2 X 4 can be used as shown to help
force and position the deck channel against the pit wall. Ensure the deck channel is level
with the pit coping, then weld the nut to the pit coping as shown.

LEVEL

Outrigger

LEVEL

Weld

Maintain

Clearence

Shim here with

plate steel if req.

50538-32 Rev. 2

\
3: Pit coping irregularities may cause gaps between the deck coping and outriggers. Shim
as needed with steel plate. Maintain proper spacing as shown, and weld the deck coping to
the outrigger, including any steel plate shims as applicable. Continue until all pit wall deck
coping has been installed.