Fairbanks 12-1492 - 12-1496 A.A.R. Combination Railroad Track/MTS User Manual
Page 20
04/12
20
50538 Rev. 7
2-F: Foundation Inspection
Excerpts from Fairbanks Scales form FF-2267; Foundation Field Check list
A Foundation Inspection should ALWAYS be performed prior to Scale installation, to confirm
the Foundation is constructed correctly and is ready for installation. If possible, this should
be done prior to the scale shipment.
TOOLS REQUIRED:
Certified drawings and site plan.
2' to 4' level
25' & 100' steel tape measures
Hammer and concrete nails
Hacksaw
laser or builders level if possible
String line (construction string)
straight edge for pit foundations
Construction Spray Paint (upside down type, for marking concrete)
Perform the following Foundation checks. It is recommended to keep a copy of the check list
with the job file. ALWAYS familiarize yourself with the CERTIFIED FOUNDATION PRINTS for
the job you are working on as model numbers and their specifications are subject to change.
1: Site Plan and Certified Prints should be thoroughly reviewed to confirm accurate locations
to the scale and all extra items ( scoreboards, lights, poles, etc.) that are included.
2: Check for truck and crane access, overhead wires, fences, green concrete, etc. .
3: Dimensional length and width check; check all 4 sides and record on chart.
4: Diagonal measurements check to verify that the Foundation is square and record on chart.
These measurements should be equal, or within ½ inch. Greater error could result in the
scale not fitting in the Foundation.
5: Check ALL pier heights to make sure they are at the correct elevation and record on chart.
6: Check the pit walls to verify they are straight.
7: Verify Ground Rod locations.
8: Verify conduit locations and pull strings.
9: Verify that drains and sump openings are piped correctly are clear of debris.
10: Check the end coping to ensure they are centerline and that the coping is correct for the
scale being installed (10', 11', 12', width, etc.). Check all coping, side and end, for hollow
areas.
11: Verify location(s) of any and all required embeds
Record all measurements and observations. Physically mark any discrepancies with the
marking paint. Do not proceed with Installation until corrections have been made.