beautypg.com

Pillar replacement steps, continued – Fairbanks Aegis Transport Scale User Manual

Page 20

background image

Section 3: Service & Maintenance

04/10

20 51191 Rev. 2

3.2.2. Pillar Replacement Steps,

Continued

7. Use two

9/16” Open-ended Wrenches

on the 3/8” x 3-1/2” Bolts through the Pillar
and on the Fastening

Nuts.

8. Remove the (2) ¼” x .50” Bolts using a

7/16” Open-ended Wrench

to loosen the

pillar from the base.

9. Carefully push the Indicator Cable through the

top Access Hole, pulling the old Pillar away
from the base carefully, tugging the cable
gently if it hangs up so not to damage it.

10. Carefully push the Indicator Cable up through

the new Pillar, and then out through the top
Access Hole.

Allow extra slack on the cable.

11. Insert the new Pillar into its hole on the Base, pulling the cable firmly at the top to

remove the slack.

12. Fasten

the new Pillar Unit to the Base with the

Nuts and Bolts.

13. Rewire the cable to the Indicator.