Then the entire end structure (two columns and crossbeam) will need to be stood up as one.

7.

Unpack the Lock Ladders (Item # 38) Figure # 2 from the package and slide them into the precut slot on

the Rub Blocks (Item # 50) Figure #1 inside each column. After removing the top nut from the lock

ladder you are ready to install the Top Caps A&B (Items # 44 & 94) Figures # 2 & 6 on the columns.

8.

Be aware of the offset hole in column Top Caps. Arrange them so that the cable mounting holes are clos

est to the runways. Use provided bolts, nuts, washers, and lock washers to install Top Caps as shown in

Figure # 2.

9.

Secure Top Cap and Lock Ladder assemblies together with Washer and Nut (Items # 40 & 41) Figure # 2.

Position the Crossbeams at the second lowest locking position on all columns.

10.

Stand up and arrange the two end structures (Columns & Crossbeams) so that the outside of the Cross

beam rail to the outside of the other Crossbeam rail measure's 184.5”. Compare the measurements from

the left and the right until they are diagonally within 1/2”. The ½” variance will help in mounting

the runways later.

11.

Lift and position each Runway into place and secure with the provided Hex Bolts, Lock Washer, Flat

Washer and Nut (Items # 34, 35, 36 & 37) as shown in

Figure # 7. The lift will square itself as you further assemble it.

Note: Install the Offside Runway (Item # 4) opposite from the Mainside Runway (Item # 5) and Power unit

Column as shown in Figure # 7.

12.

Begin cable routing installation by removing the Cable Sheaves, Shafts and Spacers from all four corners

of the Mainside Runway as shown in Figure # 4.

13.

Route and mount the appropriate Cable(s) (Items # 48, 49, 50 & 51) to each Column Top Cap, while ensur

ing that the Plastic Cable Pulley (Item # 58) is between the Cable and the Lock Ladder as shown in

Figures 1 & 8. This will allow the secondary slack cable lock to function properly. See Figure # 8

for Cable routing installation.

14.

Reinstall the Cable Sheaves, Shafts, Spacers and hardware as shown in

Figures # 4.

Note: Make sure all Cables are properly routed around Cable Sheaves.

15.

Install all Lock Rods & Linkage components per the drawing on (Page 20) Figure #5. Also, install the

Crossbeam Bracket (Item # 28) to middle / outside of each Crossbeam. Secure with the provided Hard

ware (Items # 29 & 30) Figure # 7.

16.

Mount the Power Unit (Item # 7) to the Mainside Column with the attached mounting bracket using the

Hardware (Items # 16, 17 & 103) provided as shown in Figure # 6. Once mounted, fill the Power

Unit reservoir tank with hydraulic fluid. Now, install the 90 degree Hydraulic Fitting (Item #75) Figure # 3

to the high pressure port on the Power Unit. Connect the electrical power to the Power Unit.

17.

Install the “braded” Hydraulic Hose (Item # 74) to the Fitting on the side of the Mainside Runway and at

tach the other end to the 90 degree Fitting on the Power Unit as shown in Figure # 3.

18.

Now raise the complete unit (Lift) and set at one of the bottom lock positions. Place level on crossbeam.

19.

Tighten Lock Ladder Rod Nut located on the top of each posts (Item # 41). This will raise the corner of the