Bipart delay/synchronized close, Connect batteries, Wiring – Controlled Products Systems Group CSL24V User Manual
Page 21
19
DUAL GATES ONLY + CONNECT BATTERIES
WIRING
DUAL GATES ONLY
BIPART DELAY/SYNCHRONIZED CLOSE
The LOCK/BIPART DELAY switch is used only with dual gate applications and
serves two functions:
• BIPART DELAY
SWING GATE APPLICATIONS: The BIPART DELAY is used in applications
where a mag-lock, solenoid lock, or decorative overlay would require one
gate to close before the other. The operator with the LOCK/BIPART DELAY
switch ON will delay from the close limit when opening and be the first to
close from the open limit.
SLIDE GATE APPLICATIONS: Not applicable, set to OFF.
• SYNCHRONIZED CLOSE
The BIPART DELAY is also used in applications where one gate travels a
longer distance than the other. To synchronize the closing of the gates, set
the LOCK/BIPART DELAY switch to ON for both operators.
+
+
-
-
J15 Plug
Jumper
Black Wire
Red Wire
The batteries are charged in the circuit by the integrated transformer. The batteries
are for battery backup or solar installation.
1
Turn OFF AC power to the operator.
2
Unplug the J15 plug labeled BATT on the control board by squeezing the plug
and pulling it from the control board.
3
Connect a jumper between the positive (+) terminal of one battery to the
negative terminal (-) of the other battery.
4
Connect the red wire from the J15 plug to the positive (+) terminal of the
battery.
5
Connect the black wire from the J15 plug to the negative (-) terminal of the
battery.
6
Plug the J15 plug back into the control board. This will power up the control
board.
7
Turn ON AC power to the operator.
8
Turn ON the AC power switch on the operator.
ALARM
RESET
7AH BATTERIES
CONNECT BATTERIES
(with heater)
(without heater)