d. Slowly open the shut-off valve (A) on the inlet

side of the trap.

B

e. Prime the bucket trap as follows while the

equipment is operating:

1. Close the shut-off valve (B) on the outlet

side of the trap for (1) one minute.

2. Slowly open the shut-off valve (B) on the

outlet side of the trap.

c. Open the shut-off valve (B) on the outlet side of

the trap.

b. If a gate valve (C) for test and pressure relief

is installed and it is open, close it.

C

A

B

INSTALLATION COMPLETE

a. Inspect joints for leaks. Stop all leaks by

tightening bolts (E) or replace gasket, if
necessary.

E

(x6)

INSTALLATION COMPLETE