7b
Inspect system water piping
After filling the boiler and system with water,
inspect all
piping
throughout the system for leaks. If found, repair
immediately. Repeat this inspection after the boiler has
been started and the system has heated up.
Leaks must be repaired at once.
Failure to do so can damage the
boiler, resulting in substantial prop-
erty damage.
Do not use
petroleum-based
cleaning or sealing compounds
in boiler system. Severe damage to
boiler will occur, resulting in sub-
stantial property damage.
Start-up — preparation
(continued)
7a
Final check before starting
boiler
• Read manual Section
9
including the
Operating
instructions
(Section
9c
).
• Verify the boiler and system are
full of water
.
• Verify the
Start-up preparation
procedures of Sec-
tion
7a
have been completed.
Start the boiler
• Follow the
Operating instructions
from Section
9c
to start the boiler.
• See Section
7c
if boiler fails to start.
Check system and boiler
Do not use
petroleum-based
cleaning or sealing compounds
in boiler system. Severe damage to
boiler will occur, resulting in sub-
stantial property damage.
Eliminate all system leaks
. Continual fresh makeup
water will reduce boiler life. Minerals can build up in
sections, reducing heat transfer, overheating cast iron,
and causing section failure.
1.
Check system piping for leaks
. If found, shut down boiler and repair
immediately.
.
Vent air from system
using manual vents. Air in the system will interfere
with circulation and cause heat distribution problems and noise.
3.
Inspect vent system
thoroughly for signs of deterioration from cor-
rosion, physical damage or sagging. In addition — Check for gas-tight
seal at every connection and seam.
Venting system must be sealed gas-tight
to prevent
flue gas spillage and carbon monoxide emissions which
will result in severe personal injury or death.
4.
Check around the boiler
for gas odor following the procedure of Sec-
tion
7a
of this manual.
5.
Verify operation
per Section
7b
. Perform check-out procedure in Sec-
tion
8
, and fill in the
Installation and service certificate
on the same
page.
Inspect base insulation
Check to make sure
insulation is secure
against all
four sides of the base. If insulation is damaged or dis-
placed,
do not
operate boiler. Replace or reposition
insulation.
Failure to replace
damaged insu-
lation or reposition insulation can
result in a fire hazard, causing severe
personal injury, death or substantial
property damage.
The boiler contains ceramic fiber
and fiberglass materials. Use care
when handling these materials per
instructions on
page 64
of this
manual. Failure to comply could
result in severe personal injury.