beautypg.com

Prepare water heater – Lochinvar ARMOR 151 User Manual

Page 14

background image

Installation & Operation Manual

2

Prepare water heater

Figure 2-3 Installing Propane Orifice - Model 400

Model 400

1. Remove the top and front access covers from the unit (no

tools required for removal).

2. Remove the three screws securing the venturi to the

blower.

Note: When separating the venturi from the blower,
take care not to damage the O-ring inside the blower
(FIG. 2-3).

3. Remove the four screws securing the gas valve to the

venturi (FIG. 2-3).

4. Locate the propane orifice disk from the conversion kit

bag. Verify that the stamping on the orifice disk matches
the water heater size (see Table 2A on page 13).

5. Remove the existing orifice from the O-ring in the side of

the gas valve and replace it with the orifice from the kit.
Position and secure the orifice in the valve as shown in
FIG. 2-3.

6. Reposition the gas valve against the venturi and replace

the screws (FIG. 2-3) securing the valve to the venturi.

7. Inspect the O-ring inside the blower. Handle the O-ring

with care, do not damage. Reposition the venturi against
the blower and replace the screws securing the venturi to
the blower (FIG. 2-3).

8. After installation is complete, attach the propane

conversion label (in the conversion kit bag) next to the
water heater rating plate. Attach the LP caution label (in
the conversion kit bag) to the left side of the unit in the
lower left corner.

9. Replace the top and front access covers.

ƽ DANGER

Armor 400: Inspect the O-ring when
the blower is disassembled. The O-ring
must be in good condition and must be
installed. Failure to comply will cause a
gas leak, resulting in severe personal injury
or death.

Figure 2-4 Gas Valve Adjustment - Model 501

Model 501

1. Remove the top access cover from the unit (no tools

required for removal).

2. Turn the adjustment screw on the gas valve clockwise

until it stops. Then turn the adjustment screw
counterclockwise four and three quarter (4 3/4) turns
(see FIG. 2-4).

3. Use a combustion analyzer to verify CO

2

is within

the range of 9.6 – 10.5%. If not, adjust the screw
counterclockwise incrementally to raise CO

2

and

clockwise to lower CO

2

(FIG. 2-4).


4. After adjustment is complete, attach the propane

conversion label (in the conversion kit bag) next to the
water heater rating plate. Attach the LP caution label (in
the conversion kit bag) to the left side of the unit in the
lower left corner.

5. Replace the top access cover.

ƽ WARNING

After converting to LP, check combustion
per the Start-up procedure in Section 10
of this manual. Failure to check and verify
combustion could result in severe personal
injury, death, or substantial property
damage.

ƽ WARNING

After converting to LP, check combustion
per the Start-up procedure in Section
10 of this manual. Failure to check and
verify combustion could result in severe
personal injury, death, or substantial
property damage.

14