Khldv series gas fireplace venting installation, Fp1970 firestop no room – Monessen Hearth DIRECT VENT GAS FIREPLACE KHLDV400 User Manual

Page 20

background image

20

73D0024

KHLDV Series Gas Fireplace

VentInG InStaLLatIon

2. Assemble the desired lengths of pipe and elbows nec-

essary to reach from the burner system flue up through
the firestop. Be sure pipe and elbow connections are
fully twist-locked.

3. Cut a hole in the roof using the locating hole as a center

point. (Cover any exposed open vent pipes before
cutting hole in roof). The 10

1

/

2

"x10

1/2

" (267 x 267 mm)

hole must be measured on the horizontal. Actual length
may be larger depending on the pitch of the roof. There
must be a 1" minimum clearance from the vent pipe to
combustible materials. (Insulation should be considered
a combustible material).

10

1

/

2

"

10

1

/

2

"

FP1970
firestop no room

Figure 26 - If Area Above is Not a Room, Install
Firestop above Framed Hole as Shown

Nails

Firestop

FP1970

2 ft.

Min.

2 ft. Min.

X

12

H*

FP1971

Min chimney clearance

Horizontal Overhang

Termination Vent

Lowest
Discharge
Opening

Storm Collar

Flashing

Concentric
Vent Pipe

1" Minimum
Clearances to
Combustibles

Vertical Wall

FP1971

Figure 27 -
Minimum Chimney Clearance

roof pitch

H (feet)

Flat to 6/12

1.0

Over 6/12 to 7/12

1.25

Over 7/12 to 8/12

1.5

Over 8/12 to 9/12

2.0

Over 9/12 to 10/12

2.5

Over 10/12 to 11/12

3.25

Over 11/12 to 12/12

4.0

*H - Minimum height from roof to
lowest discharge opening of vent

4. Connect a section of pipe and extend up through the

hole.

note: If an offset is needed to avoid obstructions, you
must support the vent pipe every three (3) feet. Use wall
straps for this purpose. Refer to Page 18, Figure 22.
Whenever possible, use 45° elbows instead of 90° elbows.
The 45° elbow offers less restriction to the flow of the flue
gases and intake air.
5. Place the flashing over the pipe section(s) extending

through the roof. Secure the base of the flashing to
the roof and framing with roofing nails. Be sure roofing
material overlaps the top edge of the flashing. There
must be a 1" clearance from the vent pipe to combustible
materials.

6. Continue to add pipe sections until the height of the vent

cap meets the minimum building code requirements.

note: You must increase vent height for steep roof
pitches. Nearby trees, adjoining roof lines, steep pitched
roofs, and other similar factors may cause poor draft or
down-drafting in high winds. Increasing the vent height
may solve this problem.
note: If the vent pipe passes through any occupied areas
above the first floor, including storage spaces and closets,
you must enclose pipe. You may frame and sheetrock the
enclosure with standard construction material. Make sure
to meet the minimum allowable clearances to combustibles.
Do not fill any of the required clearance spaces with
insulation.

terMInatIon HeIGHtS For VentS aBoVe
FLat or SLopeD rooFS