beautypg.com

Fp1180 max bends, Fp2134 below grade install – Monessen Hearth DIRECT VENT GAS FIREPLACE KHLDV400 User Manual

Page 17

background image

73D0024

17

KHLDV Series Gas Fireplace

VentInG InStaLLatIon

Example:

Elbow 1 = 90°

Elbow 2 = 45°

Elbow 3 = 45°

Elbow 4 = 90°

Total Angular Variation = 270°

Figure 18 -
Maximum Elbow Usage

1
2
3
4

1
2
3
4

FP1180

max bends

24"

Minimum

FP1180

A

B

10’

90°

FP2133

Horizontal run

reduction

Figure 17 -
Horizontal Run
Reduction

FP2133

The maximum number of 45° elbows permitted per side

wall installation is two (2). These elbows can be installed
in either the vertical or horizontal run.

For each 45° elbow installed in the horizontal run, the

length of the horizontal run MUST be reduced by 18" (45
cm). This does not apply if the 45° elbows are installed
on the vertical part of the vent system.

The maximum number of elbow degrees in a system is

270°. Figure 18

BeLow GraDe InStaLLatIonS

When it is not possible to meet the required vent terminal
clearances of 12" above grade level, a snorkel kit is recom-
mended. It allows installation depth down to 7" (178 mm)
below grade level. The 7" (178 mm) is measured from the
center of the horizontal vent pipe as it penetrates through
the wall.
ensure that sidewall venting clearances are observed.
If venting system is installed below ground, we recom-
mend a window well with adequate and proper drainage
to be installed around the termination area.
If installing a snorkel, a minimum 24" vertical rise is neces-
sary. The maximum horizontal run with the 24” vertical pipe
is 36". This measurement is taken from the collar of the
fireplace (or transition elbow) to the face of the exterior wall.
See the Sidewall Venting Graph for extended horizontal
run if the vertical exceeds 24".
1. Establish vent hole through the wall.
2. Remove soil to a depth of approximately 16" below base

of snorkel. Install drain pipe. Install window well (not
supplied). Refill hole with 12" of coarse gravel leaving
a clearance of approximately 4" below snorkel. Figure
19

3. Install vent system.
4. Ensure a watertight seal is made around the vent pipe

coming through the wall.

5. Apply high temperature sealant caulking (supplied)

around the 5" and 8" snorkel collars.

6. Slide the snorkel into the vent pipes and secure to the

wall.

7. Level the soil so as to maintain a 4" clearance below

snorkel. Figure 19

FP2134
below grade install

FP2134

Figure 19 -
Below Grade Installation

Screws

Minimum
4" Clearance

Ground

Window
Well

Gravel

Drain

Foundation Wall

Firestop

24"
Minimum

This manual is related to the following products: