Cell C
• SERVERS_A...G
Backup specifications for the company’s servers to prepare for disaster
recovery. Each time a new server is installed, or an existing server is upgraded,
this backup specification is updated. Schedule the backup specifications such
that Data Protector will run full backups as shown in
and level 1 incremental backups every work day.
• USERS_D...G
Backup specifications for user data. This is the main production backup at
ABC Pretoria and ABC Durban. Schedule the backup specification such that
Data Protector will run a weekly full backup as shown in
every Friday and level 1 incremental backups every work day. However, if a
full backup is carried out on Friday, then the corresponding level one
incremental backups are carried out on weekdays and then on Saturday,
skipping Friday.
on page 327 shows the backup specification configuration in greater
detail.
Table 27 ABC’s backup specification configuration
Time
Backup day
Description
Cell
Name
03:00
Saturday
IDB
A
DB_A
03:00
Saturday
IDB
B
DB_B
03:00
Saturday
IDB
C
DB_C
20:00
Friday
Microsoft SQL database
A
SQL_A
20:00
Friday
Microsoft Exchange
database
A
EXCHANGE_A
20:00
Friday
SAP database server
A
SAP_A
20:00
Saturday
SAP database server
B
SAP_B
20:00
Sunday
SAP database server
C
SAP_C
23:00
Friday
Servers
A
SERVERS_A
23:00
Saturday
Servers
B
SERVERS_B