4installation – ProSoft Technology BM-xx00-RM1K User Manual
Page 19

Installation
ProSoft Technology, Inc.
Page 19 of 48
April 21, 2015
4
Installation
4.1
Outdoor Enclosure Installation
1. Install or use an existing outdoor NEMA-type enclosure.
2. Be sure the Wireless I/O System meets applicable grounding requirements.
3. Install a 35 mm x 7.5 mm DIN rail (at least 166 mm (6.5-inch) wide) inside the enclosure.
4. Provide external power supply: 9-30 VDC.
5. Provide antenna and antenna cable to connect to Wireless I/O Radio Module.
a. There are various types of antennas including bulkhead, omni, and yagi. Please use the
appropriate type for your application.
6. Connecting a lightning arrestor is highly recommended.
7. Install antenna (performing a RF site survey prior to installation is highly recommended).
8. Make a hole on the bottom of the enclosure to run wires.
9. Run conduit for power and antenna cable.
10. Connect antenna cable to antenna and then feed cable into enclosure.
11. Feed power wiring into enclosure.
12. Repeat above steps for other site locations.