Operating Instructions

29

4.0

O

PERATING

I

NSTRUCTIONS

4.1

Startup Procedures

Before the unit is placed into service after initial installation, after equipment relocation, or after

equipment has been de-energized for an extended period of time, perform equipment inspection and

start-up procedures as detailed in 2.0 - Equipment Inspection and Startup and 3.0 - Inspection

and Startup Checklist.
After initial system startup, the following guidelines can be used for standard equipment operation.

These guidelines should be reviewed for any special equipment modifications, special site consider-

ations or company policies that may require changes to the standard equipment operation.

4.1.1 Emergency Shutdown—If Emergency Power Off switch is supplied

To perform an immediate system shutdown during emergency conditions, lift the clear protective

cover and push the Emergency Power Off (EPO) switch on the FPC’s monitoring panel.

If the site is equipped with a Remote Emergency Power Off (REPO) switch to perform an immediate

room shutdown, actuate one of the REPO switches. NEC Article 645 requires a REPO switch at the

principal exit doors.

4.1.2 Normal System Shutdown

To perform a normal system shutdown, perform an orderly load equipment shutdown according to the

load equipment manufacturer’s recommended shutdown sequence. The load equipment can be turned

OFF at each piece of load equipment or at the FPC’s output distribution (circuit breaker) panels

located behind the FPC’s front door. Turn OFF all unit output breakers, then turn OFF the unit’s

main input circuit breaker. To remove all power from the FPC, turn OFF the building power to the

FPC’s input breaker or junction box.

4.1.3 Normal System Turn ON

Make certain all of the FPC’s circuit breakers are in the OFF position. All unit circuit breakers are

located behind the front doors. Turn ON building power to the FPC. Turn ON the FPC’s main input

circuit breaker. If the circuit breaker has been tripped OFF (instead of being turned OFF), the circuit

breaker handle must be moved to the OFF position before being turned ON. If the FPC has a voltage

monitoring panel, verify proper output voltages before turning ON output circuit breakers. Turn ON

the panelboard main breakers. Individually turn ON each output circuit breaker following the load

equipment manufacturer’s startup sequence.

4.1.4 Manual Restart

If the FPC’s manual restart feature has been selected, the unit’s main input circuit breaker will be

tripped upon a power failure, preventing repetitive application of unstable voltage and allowing for an

orderly system restart. If the main input circuit breaker is tripped upon a power failure, wait until

power is restored, then follow the instructions in 4.1.3 - Normal System Turn ON.

NOTE
Depending on the particular control circuit wiring, operation of the unit EPO switch may cause

other equipment to also shutdown.