beautypg.com

Liebert fpc – Emerson Liebert FPC User Manual

Page 23

background image

Installation Instructions

19

Figure 13 Typical Liebert FPC equipment arrangement

Liebert FPC

Remote Emergency
Power Off Switch (REPO)

Ground electrode conductor
(not by Liebert ) required per
NEC for units with transformer

ƒ

3-phase , 3-wire plus ground
for units with transformer

ƒ

3-phase , 4-wire plus ground
for units without transformer

Main input power to unit
(not by Liebert )

*Transient suppression plate

Main input junction box and cable

* Flexible distribution cables
per customer specifications

* Optional devices : Refer to the
specification sheet for options
supplied

Low voltage junction
box and cable

Building interface and
alarm connections
(not by Liebert )